We built external power networks for the Amono Sp. z o.o. Stanisławów near Warsaw project.
Scope of work
- Construction of the 15kV 3x XUHAKXS cable line 1x120mm²
- Installation od the transformer station 2x630kVA
We built external power networks for the Ponetex Sp. z o.o. Skierniewice project.
Scope of work
- Construction of the cable line 15kV 3x XUHAKXS 1x120mm²
- Installation of a transformer station 400 kVA
- Lighting the area with a length of 880m YKY cables5x25mm² with steel poles 9m
We built external power networks for the Multikino Warsaw Ostrobramska street project in Warszawa.
Scope of work
- Construction of cable line 15 kV 3x XUHAKXS 1x240mm²
- Installation of the transformer station 2x 1600kVA
We built external power networks for the Outlet Fashion House in Piaseczno project.
Scope of work
- Construction of the cable line 15kV 3x XUHAKXS , 1x120mm²
- Installation of a transformer station 2x 1200kVA
- Lighting the area with a length of 1980m with YKY 5x25mm² cables with steel poles 6m, 10m, 12m, and lighting masts 25m
We built external power networks for the Spedpol Nadarzyn near Warsaw project.
Scope of work
- Construction of the cable line 15kV 3x XUHAKXS 1x120mm²
- Installation of the transformer station 2x 1600kVA
- Lighting the area with a length of 1580m with YKY 5x25mm² cables with 12m steel poles, and lighting masts 25m
We built external power networks for the Ridi Polska in Natolin near Łódź project.
Scope of work
- Construction of the cable line 15kV 3x XUHAKXS 1x120mm²
- Installation of the transformer station 1x 630kVA
- Lighting the area with a length of 480m with YKY 5x25mm² cables with 6m steel poles
We built external power networks for the Mokotów Plaza 1 in Warsaw, Cybernetyki street project.
Scope of work
- Installation of the transformer station 2x 1200kVA
- Lighting the area with a length of 280m with YKY 5x25mm² cables with 6m steel poles
We built external power networks for the Mokotów Plaza 2 in Warsaw, Cybernetyki street project.
Scope of work
- Installation of the transformer station 2x 1000kVA
- Lighting the area with a length of 280m with YKY 5x25mm² cables with 6m steel poles
- Main contractor
- STRABAG
- Location
- Warszawa
We built external power networks for the Strabag office building in Pruszków, Parzniewska street project.
Scope of work
- Construction of the cable line 15kV 3x XUHAKXS 1x120mm²
- Transformer station installation 2x 1000kVA
- Lighting the area with a length of 20m with YKY 5x25mm² cables with steel poles