SPEDPOL NADARZYN NEAR WARSAW.
A completed EL-INWEST project in the external power grids category, located in Warszawa.
ROLE OF EL-INWEST.
We built external power networks for the Spedpol Nadarzyn near Warsaw project.
Scope of work
- Construction of the cable line 15kV 3x XUHAKXS 1x120mm²
- Installation of the transformer station 2x 1600kVA
- Lighting the area with a length of 1580m with YKY 5x25mm² cables with 12m steel poles, and lighting masts 25m